704.14(c) Petitions to Requirements Under 37 CFR - 700 Examination of Applications
704.14(c) Petitions to Requirements Under 37 CFR 1.105
Applicants who seek to have a requirement under 37 CFR 1.105 withdrawn or modified, or who seek to have information submitted under 37 CFR 1.105 considered, may submit a petition under 37 CFR 1.181 to the Director of the Technology Center in which the requirement was issued. However, a petition is not a reply to a 37 CFR 1.105 requirement. The time period for the applicant to reply to the 37 CFR 1.105 requirement continues to run, even where a petition has been submitted.